
A remodel's real calendar starts at the first phone call, not at demolition. Here is what each phase takes, and what makes some projects run long.
When people ask how long a remodel takes, they usually mean how long a crew is in the house. That is the shorter half of the answer. The real calendar runs from your first phone call to the final walkthrough, and the planning half often takes as long as the building half.
That planning time is not wasted. It is what keeps the construction phase short. Every decision settled on paper is a decision that will not stop work later. When a homeowner in Lakeville or Eagan tells us they want to be done by Thanksgiving, we count backward through all of it, not just the weeks of hammering.
What follows is what each phase typically takes and what stretches a schedule. Treat every number here as typical, not promised. Your house, your city's permit office, and your material choices all move it.
The first call is short. We talk through what you are hoping to do, answer your early questions, and get an in-home consultation on the calendar. Scheduling that visit usually takes a few days to a couple of weeks, since spring and early summer are the busiest stretch in the south metro.
The consultation is a single visit. We review the layout of the space, design ideas, finish materials, your needs and wants, and your budget. You leave with a rough budget range. No drawings yet and no line-item price, just an honest read on whether the project you are picturing and the number you have in mind belong together.
If they do not line up, better to learn it in week one than week ten. Projects change shape at this stage all the time, and reshaping one at a kitchen table costs an afternoon.
If you want to move forward, we enter into a Pre-Construction Services Agreement. It covers permit-ready floor plans, coordination of your design and finish material selections, a detailed investment cost, a progress payment schedule, and an estimated construction time frame. How long it takes varies with the size of the project and how quickly selections get made, but a few weeks is common.
Size is on us. Pace of selections is on you. You get a written selection list with the showrooms we work with: cabinetry in Rosemount, countertops in Apple Valley, tile in Eagan, plumbing fixtures and shower glass in Burnsville, flooring in Apple Valley and Lakeville, and windows, doors and trim here in Farmington. Most of them require appointments, and the list asks you to mention you are working with MDR when you book.
Book those appointments the week you get the list and this phase moves at the fast end of normal. Take a month to choose tile and the whole phase waits on tile. At the end you have drawings a building department will accept, a specific list of what is going into the house, a real price, and a payment schedule. A completion date offered before those exist is a guess.
Once plans, selections, and the detailed estimate are approved, permits are applied for, material is ordered, and the schedule is finalized. We obtain the required building permits. Review time belongs to your city and varies a great deal, since a straightforward interior permit usually moves faster than an addition needing structural and zoning review. Your building department sets that timeline and confirms what your project needs at permit.
Lead times are usually the longer half of this phase. Stock vanities and in-stock flooring arrive quickly. Semi-custom and custom cabinetry runs weeks to months. Windows, especially custom sizes and specialty units, are often the single longest lead item on an addition or whole-home project. We order long-lead material as soon as selections are final, which is why we push to get selections final.
We also will not start demolition until the sequence works. Tearing out your only bathroom and then waiting on a shower base that has not shipped helps nobody. Ordering ahead is not a delay. It prevents one.
The ranges below are typical construction windows for the south metro, measured from the day we set floor protection to the day we walk the finished space together. They assume plans are set, material is on hand, and nothing unusual turns up behind the walls.
A bathroom commonly runs about three to six weeks. A powder room is quicker; a primary suite with a custom tiled shower is slower. A kitchen commonly runs about six to ten weeks, and longer when walls move or plumbing relocates. A finished basement usually falls somewhere between six and twelve weeks depending on square footage, whether there is a bathroom or wet bar, and how much mechanical rerouting is involved.
An addition generally runs three to six months, because it adds excavation, footings, framing, roofing, and a full run of inspections, and Minnesota weather affects the early stages. Whole-home remodels vary the most, commonly four to nine months, since they are really several projects sequenced together.
Add the planning half back in and the honest answer for most kitchens and baths in Apple Valley, Burnsville, or Prior Lake is several months from first call to finished. For an addition, plan on most of a year.
Late selections, first and by a wide margin. A cabinet order waiting on a door style, or a shower waiting on a tile decision, pushes every trade behind it. Once a slot is missed, the next crew has committed to another job, so you are waiting on their calendar too.
Long-lead items are second. Custom cabinetry, specialty windows, made-to-order fixtures, and slab stone set their own pace. Inspections are third. Work pauses at each required inspection until it passes, and inspectors work on the city's calendar, not ours.
Then there is what demolition uncovers. Older homes across the south metro hide water damage, rot, mold, structural deficiencies, and previous work that was never done right. Our contract commits us to notify you immediately, and corrective work is performed only after written approval through a Change Order. That protects you from surprise billing, and it also means the clock waits on your decision.
Our contract is direct about the rest. The dates in it are estimates until a final schedule is set, and they can move for weather, material availability, owner-requested changes, hidden conditions, permit or inspection delays, and events outside our control. Changing your mind mid-project is allowed. It is just never free, in dollars or in days.
Make selections early and hold them. Book the showroom appointments the week we hand you the list. Every choice locked before construction starts is a day you are not losing later.
Handle your side of setup. Our contract asks you to clear the work area of furniture, wall hangings, and personal belongings before we start, secure pets, provide reasonable access, and keep the electrical panel and water main shutoff clear. On day one that is the difference between a crew that starts working and a crew that starts moving your things.
Answer questions the same day. Plan around the hours as well: construction runs 7am to 5pm Monday through Friday, so if you work from home, set up somewhere the noise will not matter. If you are in an association, start the HOA approval early. That approval is the homeowner's responsibility unless we have specifically included it, and boards meet on their own schedule.
The traditional path is to hire a designer or architect, wait for drawings, then send those drawings out to contractors and wait for bids. Every handoff has dead time in it, and bidding can end with plans that need reworking because the price came back higher than the budget, which restarts the design clock.
In design-build, one team draws it, prices it, and builds it. Pricing happens alongside design, so budget is a running conversation instead of a verdict at the end. Nobody waits on plans to be handed between companies, and nobody redesigns to hit a number they found out about too late.
It also removes the back-and-forth that quietly eats days. When the people who designed your space are accountable for building it, a field question gets answered that afternoon.
The last stretch surprises people. Final trim, paint touch-up, hardware, shower glass, and appliance hookups are all short tasks, but each brings a different trade back for a few hours, and coordinating those visits takes time. Leave a week or two at the end for it.
Before final payment we walk the project together and address the punch list. We do a final cleanup, and manufacturer warranties pass directly to you. Workmanship is covered by our one-year warranty from the date of substantial completion, so if something shows up after you have lived in the space, you call and we come back.
That walkthrough is the real end of the calendar. If you want a realistic timeline for your own house, call 952-846-8115 and we will count it out with you, phase by phase, before you commit to anything.

Dust, noise, work hours and kitchen workarounds — what it is actually like day to day.
Read the Guide
What to pick first, how lead times drive your schedule, and where allowances go wrong.
Read the Guide
What kitchens, baths, basements and additions actually run in the south metro, and what moves the number.
Read the Guide
Book a free consultation and let’s talk it through — no pressure, no obligation.